Discussion about this post

User's avatar
Cape Fear Advisors's avatar

Correction and update, dated August 18, 2026.

This piece said August 26 would settle which of four accounts described the instrument correctly. A filed document settled it nine days early, and it was on EDGAR before this piece published.

NVIDIA filed a Form 8-K on August 17 at 8:41 am Eastern under Items 1.01, 2.03 and 7.01, accession 0001045810-26-000069. The instrument is named: "multiple residual value guaranties" with SB Energy as lessor, covering approximately 4.25 gigawatts of IT load at the PORTS Technology Campus, OpenAI as tenant, cumulatively capped at $105 billion for the initial commitment, with credit support for approximately 3.8 gigawatts more at NVIDIA's sole discretion. Payment obligations begin at ready for service, expected from 2028. The form of the agreements will be filed as an exhibit to the Form 10-Q for the quarter ended July 26, 2026.

Four consequences for what is above.

Note (11) is wrong as published. It says no Form 8-K from NVIDIA on the Ohio commitment was on EDGAR as of the date of this piece. The filing was accepted about six hours before publication. The probe behind that sentence was run earlier and was not re-run at print. An absence claim carries the time it was checked, and this one carried the wrong time.

The four accounts resolve, and less cleanly than a scoreboard suggests. NVIDIA's own August 10 language, the fourth account here, matches the filed instrument name. The Journal's asset value reading matches the measure: payment is the shortfall between a guaranteed minimum lease value and what a replacement lease or a sale recovers. The Axios lease and power payments reading matches the trigger: OpenAI insolvency resulting in lease default, or failure to make lease payments. The two accounts this piece set against each other as opposites were describing different halves of one instrument, one the trigger and one the measure. That is a better answer than the piece anticipated and it is fairer to both outlets.

The per gigawatt qualification needed the filed perimeter, and now has it. The initial commitment covers 4.25 IT gigawatts, so the filed ceiling is about $24.7 billion per IT gigawatt. Set against the late July figure of about $250 billion for the whole site, the fall per gigawatt is about 21 percent if that site is read at the 8 IT gigawatts the company's own release now gives, and about 1 percent if it is read at 10. The headline fall of 58 percent is unchanged and the perimeter accounts for most of it, which is what the qualification in this piece said it might.

August 26 changes job. It confirms and quantifies rather than identifies. The fiscal quarter end is now filed as July 26, 2026, which closes a question this piece answered from the calendar.

The water finding survives its first filed test. "Water" and "Scioto" appear zero times in the 8-K and zero times in the furnished release.

No posts

Ready for more?